Grace Victoria Quarter has had an incredible year in 2016, from its launch in March to commencing construction in September. As we head into Christmas, our construction programme is making excellent progress.
Macrennie has now completed Stage 1 of demolition, with Stage 2 to take place later this month. This will include the demolition of the lower northern Cook Street end of the site, down towards Sale Street.

Half of the building piles have been installed at the southern Cook Street end of the site, and capping beams are being prepared on top of these piles. Once excavation is complete, foundation works will commence to prepare for the basement car park levels.